What Information Does a Billboard Tower Manufacturer Need Before Quoting? | QX Outdoor

Views:83
Update time:2026-10-30

Answer: Provide the installation country and site, billboard type, number and arrangement of faces, display dimensions, overall height, intended display material, maintenance access requirements and local design codes. Share wind criteria, exposure, geotechnical data, foundation constraints, desired finishes and delivery destination. An engineer must verify the design inputs before a firm structural quotation.

Billboard pole base plate with stiffeners and anchor bolts on a concrete foundation

Site and Wind Information

Wind load governs the entire structure, so the site address is the first input.

  • Project address, country and whether the site is coastal or exposed

  • Design wind speed from the local code, or the code reference so we can derive it

  • Terrain category and surrounding obstruction if known

  • Seismic requirement, where the local code applies one

Structure and Display Information

Panel size and height decide the pole section and the foundation loads.

  • Panel width and height, and single or double sided configuration

  • Mounting height from ground to the bottom of the panel

  • Display type: printed panel, trivision prism or LED screen with its weight

  • Access requirements for maintenance, catwalk and lighting

Commercial and Logistics Information

These decide the packing plan, the price basis and the delivery date.

  • Quantity of towers and whether a repeat programme is expected

  • Destination port and preferred Incoterm

  • Local constraints on transport length and crane capacity

  • Required on-site date and permit timeline

Frequently Asked Questions

What if I do not know the design wind speed?

Give us the address and we will propose a value from the applicable code for your confirmation, clearly flagged in the quotation so your local engineer can verify it.

Does an LED screen change the structure?

Yes. Screen weight, wind area and maintenance access change the arm and pole design, so the screen specification must be provided before fabrication.

How detailed should the foundation information be?

At minimum the soil type and water table. A geotechnical report is better and usually reduces steel and concrete.

Get a Firm Billboard Quotation

Send site location, panel size and display type, and we will return engineering parameters, drawings and price within 48 hours.